Work Method Statement PDF Print E-mail
Article Index
Work Method Statement
Page 2
Page 3
Page 4
Page 5

This is an Example

Ref: ALLIED/08

ALLIED DISTILLERS Ltd - GLASGOW ROAD

HOT Pressure Wash/HPWJ FUSEL Oil Systems & Vessels OPERATION(S)

  1. Obtain Permit To Work & Permission to proceed.
  2. Establish service area for plant & equipment etc.
  3. Cordon off service area with barrier tape / warning notices.
  4. Set up & test Water Jetting Equipment & Steam Cleaning Unit.
  5. Proceed with operation to clean Fusel Oil System

Manpower On Site: Skilled Operatives.

Plant / Equipment: 1 High Pressure Water Jetting Unit & 1 Hot Pressure Wash unit.

Protective Clothing: PVC Wetsuits & gloves, Safety footwear, Head protection, face visor.

Arrival on site

Acre's manpower, plant and equipment will arrive on site at a time and date as agreed by Allied Distillers Ltd.   Acre's employee in charge of this operation will establish contact with the site representative to confirm service area for setting up equipment.

ADL Responsibilities

  • Site Safety Inductions must be carried out by ADL.
  • ADL must ensure that relevant system isolations have been carried out.
  • Any associated systems which are normally pressurised must be de-pressurised and drained prior to commencement of any.
  • Any dismantling or re-assembling of systems will be carried out by ADL personnel.  Removal and replacement of vessel access covers / flanges will be carried out by ADL personnel.
  • ADL must ensure safe access / egress to the site at all times. 
  • Machinery guards must be properly fitted to any live or running machinery in the vicinity of Acre Industrial cleaning operations.
  • ADL must issue a Permit To Work for all operations. Work Permits should confirm that correct isolations,  where appropriate, have been carried out and that the FUSEL oil system is safe to work on.
  • ADL must provide material data sheets for any potentially hazardous substances which Acre employees may be exposed during cleaning operations.
  • ADL must ensure that all associated vessels are drained down prior to commencement of operations.